From Drawings to Opening Day: A Multi-Zone Indoor Adventure Park Build
Project Snapshot
This case follows a build we completed for a multi-attraction indoor park inside a shopping mall: a single floor plate that had to carry a trampoline arena, a soft play complex, a four-lane stainless speed slide, two ball pits, an interactive projection wall, a reaction game and a toddler garden, all inside an existing retail shell with the mall’s columns already standing in the middle of it.
The photographs in this case are taken on site after opening, not renders. What they show is the part that a 3D image cannot show: how padded columns meet an existing concrete column, how a stainless tube slide is welded and flanged at the joints, where the neon signage was hung from, how ball-pit balls sit against a glowing portal, and how the floor graphics actually read under mall lighting.
We acted as manufacturer and build partner: layout, steel, soft-play modules, slides, padded columns, floor print, signage frames and installation guidance. The operator kept control of their own ticketing, staffing, FEC brand and retail mix, and we designed around their ceiling, their columns and their opening date rather than the other way around.

| Project Item |
Detail |
| Venue type |
Multi-attraction indoor adventure park inside a trading shopping mall |
| Client |
Indoor park operator, name withheld on request |
| Audience |
Children aged 2-12 with adult supervision, plus school and party groups |
| Format |
Single floor plate, open plan, eight attractions sharing one circulation route |
| Existing conditions |
Structural mall columns inside the play field, service sprinklers at low level, solid mall floor, limited night-time access for installation |
| Delivered scope |
Steel frames, honeycomb and soft-play modules, stainless tube slides, padded column wraps, ball pits, projection wall housing, reaction game, toddler garden, printed floor, neon signage frames |
| Basis of figures |
Counts below are taken from the as-built layout and site photographs; areas are design references pending final site survey |
| Status |
Installed, open and trading |
What the Site Handed Us
Three site conditions shaped the design more than any theme decision.
Columns in the middle of the floor.
The mall’s structural columns stood exactly where a play field would normally sit. Removing them was impossible, and building around them usually leaves dead corners. We wrapped them instead: orange and blue neoprene bands over foam, striped in white, with a brushed stainless guard at adult height and a padded base plate at floor level. The columns became the park’s striped forest rather than an obstacle, and one of them now carries the height chart gate that children check themselves against on the way in.

A ceiling that varies, with services hanging low.
Sprinkler runs and cable trays crossed the play zone, so every tall element had to be placed against a measured ceiling survey rather than a nominal height. The four-lane stainless slide, the honeycomb tower and the net dome were each set to their own clearance, and the neon signage was hung from independent frames so it never loads a sprinkler pipe.

Night-time installation access only.
The mall traded during the day, which meant deliveries and steel erection happened after closing and had to be clean enough for shoppers by 9 am. That pushed the build toward bolted modular frames and pre-finished panels: nothing was painted or welded on site in the public hours.
Design Response: Eight Zones, One Route
The park is not a collection of separate rides with separate queues. Each zone is placed so that a child moving at speed and a parent moving slowly end up on two different lines, and so that one attendant can see two adjacent zones without walking between them.
Candy Stripe Spiral Slide Tower
A red and white striped spiral tube wraps a tower wrapped in black and white banding, with one clear polycarbonate segment halfway down so the ride is visible from outside and debris is visible from the landing. The exit is a wide gloss-black open flume that flattens onto an orange landing pad, which keeps the last metre slow and the arrival predictable. Children enter from the upper deck behind the tower, so the queue never forms on the public floor.
Neon Ring Portal and Ball Pit
A circular portal of concentric glowing rings, magenta to violet, sits at the end of a red wall and opens into a ball pit filled with white and chocolate balls. The rings are the park’s best photograph and its most obvious landmark: children aim for the portal from across the floor, which pulls foot traffic toward the pit instead of the stairs. The portal frame is a moulded shell with a padded surround, and the inner opening is meshed so the pit cannot be entered through the ring itself.

Honeycomb Hex Structure
A honeycomb wall of hexagonal cells in yellow frames over a blue body, with mesh behind each cell so children can climb through, look out and drop blocks into the cells from above. LED edge lighting runs around the frame, which turns the structure into a lit object at night and carries the park’s identity into the darker half of the hall. The cells are sized so an adult can reach into any one of them, and the base cells open at floor level for toddlers who cannot climb yet.
Four-Lane Stainless Speed Slide
Four mirror-finish stainless lanes drop from an upper deck and land on four separate purple mats, each offset so a child arriving at speed cannot cross into the lane next to them. The tubes are welded and flanged at the joints, polished after fabrication, and the last section is a shallow open flume that slows the slide before the mat. Above, the orange checkerboard wall doubles as the mount for the slide frame, so the structure is tied into the soft-play body rather than standing as a separate tower.

Swirl Cone Climbing Volcano
A large cone clad in a teal and white swirl pattern stands as a climbing feature, with holds set into the surface and a soft crater at the top. It is the park’s vertical challenge for older children and its most photographed backdrop for younger ones, and it sits beside the spiral slide so the two share one supervision post.
Interactive Projection Ball Pit
A projection screen is set into the pit wall under a decorative eave, turning the ball pit into a game surface: balls thrown at the wall register on screen, scores appear at the top corner, and children play in teams without a staff member calling the rules. The screen housing sits behind a padded frame, cabling runs outside the play volume, and the projector is serviced from the back of the wall rather than from inside the pit.

Reaction Height Post Game
Five white posts rise from an orange circular platform, each collared with a printed height: 0.8, 1.1, 1.5 and 1.85 metres, with a floor target of concentric rings and a lit instruction disc. Children hit the target, then race to touch the post that matches their height, which turns a queue into a timed game and gives the park a low-cost, high-turnover attraction that needs no attendant beyond a start signal.
Trampoline Arena and Net Dome
The trampoline field is laid over orange and red mats with orange padding between beds, and a large net dome spans the arena above head height. The net is both a safety envelope and a visual signature: it lets the arena run at a lower ceiling clearance and stops a bouncer from leaving the field. Climbing holds, a lit scoreboard and a shoe rack sit at the arena edge, so entry, briefing and shoe change happen in one place.
Toddler Garden
A pastel garden behind an arched pink fence holds an orange mushroom softie, a green rocker, ride-on cars and a printed road with a crosswalk. The fence arches are cut as windows rather than solid panels, so parents see in from outside and toddlers see out, which keeps the youngest zone calm without making it a closed box. The floor print continues the road from the main hall, so a toddler can follow the same line the older children use.
Zone Schedule at Handover
The table lists the eight zones as installed, with the element count that drove fabrication and the supervision note agreed with the operator.
| Zone |
Installed Count |
Primary Age Band |
Supervision Note |
| Candy stripe spiral slide |
One tower, one tube, one clear segment, one landing pad |
4-9 |
Entry held on the upper deck, exit watched from the pit side |
| Neon ring portal and pit |
Three concentric rings, two ball mixes |
2-10 |
Ring opening meshed; pit entry counted at the parapet |
| Honeycomb hex structure |
Nine hex cells, LED edge strip, mesh backing |
2-8 |
Floor cells open for toddlers, upper cells watched from the deck |
| Stainless speed slide |
Four lanes, four landing mats, one upper deck |
6-12 |
One child per lane, called by lane number at the top |
| Swirl cone climb |
One cone, holds set in a spiral, soft crater top |
6-12 |
Shares the slide post; no queue allowed at the base |
| Projection ball pit |
One screen, one projector box, two ball mixes |
4-10 |
Game resets on a timer; screen serviced from behind the wall |
| Reaction height game |
Five posts at 0.8, 1.1, 1.5, 1.85 m plus one marker post |
5-12 |
Start signal only; one child per round on the target disc |
| Trampoline arena |
Bed field, padded dividers, one net dome, entry rack |
5-12 |
Timed session, sock check, one bouncer per bed |
| Toddler garden |
Arched fence run, two softies, four ride-ons, printed road |
2-5 |
Adult required inside; fence arches kept open for sightlines |
Engineering Decisions That Made It Buildable
Most of the decisions in this build were made so that the finished park would still be serviceable two years later. The table below lists what was specified and why it mattered on this site.
| Element |
What We Specified |
Why It Mattered Here |
| Existing columns |
Foam sleeve with neoprene bands, white tape stripes, stainless guard at adult height, padded base ring |
Kept the mall structure, turned an obstacle into the park’s striped identity, and left the guard where trolleys and adults hit |
| Stainless slide tubes |
Welded and flanged joints, mirror polish, open flume at the exit, separate mats per lane |
High-traffic lanes take abrasion better than plastic, and the four separate landings prevent cross-lane collisions |
| Spiral slide clear section |
Toughened polycarbonate panel, bolted flange, replaceable as a single segment |
Parents see the ride from outside; maintenance sees debris without dismantling the tube |
| Honeycomb structure |
Moulded hex frames, mesh backing, LED edge strip on 24 V, floor-level cells opening at the base |
Reads as a lit landmark after hours, and toddlers can use the base without climbing |
| Projection wall |
Screen housed behind padded frame, cabling and projector inside a service box, back access |
No electrics inside the play volume, and the projector is serviced without entering the pit |
| Reaction game |
Five PVC posts with numbered collars, printed height marks, lit instruction disc |
Turns an unstructured queue into a timed game with no staff required beyond a start signal |
| Trampoline arena |
Orange bed surround, padded dividers, large net dome above, shoe rack at entry |
The net allows a lower ceiling clearance and keeps bouncers inside the field |
| Signage |
Neon flex on independent steel frames, mounted clear of sprinkler runs |
No load on mall services, and lettering can be changed without touching play structure |
| Floor |
Printed PVC wear layer, road and crosswalk graphics, separate printed sheets per zone |
Zones can be replaced individually, and the road system doubles as a circulation map |
| Ball pits |
White and chocolate ball mixes at a fixed ratio, bay dividers, sump for draining |
Top-up orders stay predictable, and bays can be washed while the park trades |
Safety and Compliance Work
The park mixes soft play with trampoline, stainless slides and projection equipment, which means the compliance work had to cover four different equipment categories in one hall. The table below summarises the checks we ran before handover.
| Check |
What Was Verified |
| Materials |
Foam density, PU cover thickness, flame retardancy, ball material and slide resin tested to CE, ASTM F963 and EN71 references |
| Steel and fixings |
Frame load test, bolt torque check, anti-rust coating, no exposed bolt heads inside the play volume |
| Slide run-off |
Run-out length checked lane by lane with a weighted test bag, mats positioned to catch the slowest arrival |
| Fall zones |
Padding depth measured under every elevated exit and platform, including the honeycomb upper cells and the cone top |
| Mesh and gaps |
Mesh aperture checked against head and limb entrapment, gaps at joints measured at every tower opening |
| Electrics |
LED strips, neon signage and projection equipment on 24 V or isolated circuits, drivers outside the play volume |
| Net dome |
Net tension, anchor points at each mast, perimeter seam check and a climb test at the strongest point |
| Sprinkler clearances |
Signage and structure set clear of mall sprinkler heads and cable trays, verified with the mall engineer |
| Handover file |
Assembly drawings, load test record, material certificates, maintenance schedule and spare parts list |

Installation Sequence
Because the mall opened every morning, the build ran as a series of night shifts with a clean hand-back each day. The sequence below is the one we would use again for a trading-mall site.
-
Survey and setting out. Ceiling heights, column positions, sprinkler locations and floor level were measured and reconciled against the drawings before any steel arrived.
-
Column wrapping and floor base. Existing columns were sleeved and banded first, so every later element could be set against a finished reference line rather than a raw core.
-
Main frames and upper decks. Bolted modular frames went up overnight, with the upper deck and stair footprints finished before the slides arrived.
-
Slides, honeycomb and portals. Stainless lanes were welded and flanged, the spiral tube was assembled in sections through the clear panel, and the neon ring portal was set last because it is the most visible element from the mall corridor.
-
Soft play, pits and games. Padding, ball fills, projection, reaction posts and the toddler garden followed, with the trampoline arena finished before the net dome was tensioned.
-
Testing, cleaning and handover. Run-out tests, ball depth checks, lighting and projection calibration, then a full clean so the park opened to shoppers rather than to a building site.
What the Layout Changes in Daily Operation
These are operational consequences of the design, not marketing claims. They are the points an operator should check on any similar project.
One attendant can hold two zones. The spiral slide exits beside the cone and the neon portal, and the four stainless lanes land in a row, so a single station covers slide traffic and pit entry at the same time. On a busy Saturday that is one fewer person on the floor than a scattered plan would need.
Queues live inside structures, not on the public floor.
The candy slide holds its queue on the upper deck, the honeycomb holds children inside its cells and the reaction game self-sequences with a start signal. The floor stays walkable, which matters when a parent is pushing a stroller through a mall unit.
Every zone has a photograph inside it. The portal rings, the honeycomb wall, the stainless lane bank and the neon sign each frame a child against a distinct background. Guest photography spreads across the hall instead of stacking at one wall, and the operator gets four usable images for listings and campaigns from one fit-out.
Wear is concentrated where it can be replaced. Slide run-outs, mats, ball mixes, column bands, net panels and floor sheets are all modular. A refit in three years is a parts order, not a rebuild, which is the main financial argument for buying a build like this rather than a painted set.
What We Would Do Differently
-
Measure the ceiling earlier: two elements were re-detailed after the sprinkler survey came back lower than the base drawings showed.
-
Print the floor in more, smaller sheets: zone-level replacement is easy, but a single large sheet across a road junction is harder to lift later.
-
Fix the height-chart gate position during design, not on site: it ended up on a wrapped column, which works well, but the decision was made late.
-
Order spare ball mix with the first delivery: pits lose volume from day one, and a matching top-up later costs more in freight than in balls.
-
Agree the night-shift hand-back checklist with mall facilities in writing: cleaning expectations are the usual source of friction, not the build itself.
Scope and Cost Structure
Buyers usually ask what a build like this actually contains. The table below groups the scope the way we quote it, so an operator can compare against other suppliers line by line.
| Scope Group |
Included in This Build |
Note for Buyers |
| Structure |
Galvanized frames, upper decks, stairs, tower bodies, honeycomb module, cone shell |
Ask for the load test record and the steel wall thickness, not just the drawing |
| Slides |
Stainless four-lane bank with welded joints, striped spiral tube with clear segment |
Stainless costs more up front and less over five years than plastic on high-traffic lanes |
| Padded works |
Column wraps, parapets, stair treads, bed surrounds, portal frames, toddler fence |
Specify cover thickness and whether covers are removable for washing |
| Play media |
Two ball pits with mixed fills, ride-ons, soft rockers, blocks and props |
Agree the ball ratio and a top-up allowance in the contract |
| Interactive |
Projection wall with housing, service box and calibration; reaction height post game |
Confirm who maintains the projector and the game software after handover |
| Trampoline |
Beds, surrounds, dividers, net dome, entry rack |
Check bed replacement cost and delivery time; beds wear before frames do |
| Floor and signage |
Printed PVC floor per zone, road graphics, neon signage on independent frames |
Ask for the print files; zone-level replacement depends on having them |
| Documents and support |
Assembly drawings, certificates, maintenance schedule, spare parts list, remote video support |
Insist on a maintenance schedule with intervals, not a generic manual |
Takeaways for Operators Planning a Similar Build
Four things in this project are worth copying, and one is worth avoiding.
First, treat the mall’s existing columns as material, not as an obstacle: wrapping them is cheaper than designing around them and usually becomes the park’s most recognisable feature. Second, put the queue inside the attraction, whether that is an upper deck, a honeycomb cell or a timed game, because public floor space is the scarcest resource in a retail unit. Third, buy stainless where traffic is highest and plastic where it is not, and separate the landing mats so lanes cannot cross. Fourth, give every zone its own backdrop, because the images a park produces are the cheapest marketing it will ever own.
The thing to avoid is a themed set that cannot be repaired piece by piece. A park of this size will lose balls, wear mats, crack a clear panel and dim a neon strip within two years. If those parts are modular, the park keeps trading through the repair; if they are not, the operator closes a zone to fix a slide.
Talk to Us About Your Site
If you are planning an indoor park in a mall, a retail unit or a converted industrial shell, send us your floor plan, ceiling height, column grid and target age mix. We will come back with a zone plan, a build sequence and a line-by-line scope so you can compare this kind of build against whatever else you are being offered.